Now that the cat is out of the bag and the Japanese government has officially announced Kengo Kuma's stadium proposal as the new winning design for the 2020 Tokyo Olympics, all eyes are on Zaha Hadid Architects, design firm of the voluptuous initial winning stadium spaceship which was ultimately... View full entry
The government on Tuesday picked a design by architect Kengo Kuma for the new National Stadium, a building that is expected to become the centerpiece of the 2020 Tokyo Olympics.
One of two short-listed entries and identified until now only as design A, Kuma’s plan was a joint submission in partnership with construction giant Taisei Corp.
The competing design, identified as design B, was by architect Toyo Ito [...].
— japantimes.co.jp
Last week's rumors turned out to be true - the winning Design A was indeed developed by Kengo Kuma & Associates, beating out Toyo Ito's less successful Design B.UPDATE: Zaha Hadid issues disappointed statement on Tokyo Olympic Stadium decisionPreviously in the Archinect news:Kengo Kuma &... View full entry
Wood latticework, green shrubbery, sunken sports fields and temple-like touches can be seen in the two final design proposals for Tokyo’s controversial new Olympic Stadium. [...] The new proposals [...] are more understated in style and also smaller in physical form compared to the originally commissioned design. [...]
The agency has not named the firms behind the two final designs, although unconfirmed local media reports stated that they were Kengo Kuma and Toyo Ito [...].
— telegraph.co.uk
Design A - rumored to be by the office of Kengo Kuma.Design B - believed to come from Toyo Ito's firm.Which design is your immediate favorite? Who is going to finally build the Japan National Stadium? Let us know in the comment section.UPDATE: Kengo Kuma selected for new Tokyo Olympic... View full entry
'We’re expecting at least 10,000 applications this time,' said Ryohei Miyata, head of the selection committee.
Only 104 applications were accepted for the previous competition.
Applicants this time only have to be 18 or older and a resident of Japan. The committee will accept an entry by a group if the leader of the group meets the age and resident criteria, meaning that people younger than 18 can still take part.
— The Japan Times
After the Tokyo Olympics organizing committee ran into accusations of plagiarism with their first logo for the Games, the committee is at it again with a second call for submissions. But this time around, they're inviting virtually all residents of Japan to submit their ideas for a new logo... View full entry
Tokyo-based Robot Taxi ... is still on track to start field tests of its driverless taxi service in one region of Japan by the end of next March [...]
The company, a joint venture between DeNA (one of Japan’s mobile internet pioneers) and ZMP (a robotics firm; tagline “Robot of Everything”) is not building its own cars from scratch. Instead, it’s focusing on adding driverless capabilities to existing cars and designing, creating, and marketing the taxi service.
— qz.com
More on the lead-up to Toky's 2020 Olympic Games: Zaha Hadid ineligible to participate in Tokyo Stadium design-build competitionJapanese government hopes to cap Olympic stadium costs at US$1.28 billionZaha's Tokyo Olympic Stadium cancelled – Abe calls for a redesign from scratch View full entry
In the headache-inducing whirlwind regarding Japan's New National Stadium for the 2020 Tokyo Olympics, Zaha Hadid Architects and Japanese engineering company Nikken Sekkei announced their ineligibility to participate in the design-and-build competition for the stadium's redesign. Why? Because they... View full entry
The government hopes to cap the cost of building the main stadium for the 2020 Tokyo Olympics at ¥155 billion, much lower than the ¥252 billion projected under a recently scrapped plan [...].
The government intends to make sure that the stadium will be built by April 2020. But given the International Olympic Committee’s request that the venue be built by January of that year, it plans to ask a yet-to-be-named contractor to propose shortening its construction schedule, the sources said.
— japantimes.co.jp
Read more about the troubled New National Stadium Tokyo in the Archinect news:Not over yet: Zaha Hadid releases 23-minute film pushing for Tokyo Olympic StadiumAre uncompetitive Japanese contractors to blame for Zaha's New National Stadium budget blowout?Zaha Hadid reportedly not giving up on... View full entry
In an architectural "hail Mary" move, Zaha Hadid Architects put out a 23-minute video stating their case for Japan to keep their embroiled design for the 2020 Tokyo Olympic Stadium. When Japanese prime minister Shinzo Abe announced approximately five weeks ago that ZHA's design was being dropped... View full entry
Zaha Hadid, the architect whose plans for the National Stadium have been scrapped, hopes to remain involved in the planning for the centerpiece for the 2020 Olympics, the Japan Sport Council said Thursday.
The council said Jim Heverin, a director of Hadid’s company, conveyed her wishes on a fact-finding visit to Japan following the cancellation. [...]
Meanwhile, it has been revealed that Japan faces a ¥5.9 billion bill for the work done so far and contracts already signed.
— japantimes.co.jp
Despite Japanese Prime Minister Shinzo Abe pulling the plug on Hadid's stadium design last week due to the unforeseen astronomical costs, the Japan Sport Council is nonetheless on the hook now for ¥5.9 billion (nearly $48 million) for the work that had already been done so far by various... View full entry
After multiple reassurances that Zaha Hadid Architect's design for the Tokyo Olympic Stadium would continue, despite skyrocketing costs since its 2012 announcement and constantly decreasing public favor, Japanese Prime Minister Shinzo Abe announced today that the stadium would be scratched in... View full entry
The price tag for 2020 Tokyo Olympic stadium is now a whopping $2.1 billion. That’s more than the stadiums for the past three summer Olympic stadiums combined. That’s pretty silly! So is the stadium’s new Photoshop meme. — kotaku.com
With the current estimated cost for Zaha Hadid 's stadium design clocking in at more than $2 billion (that's $700 million more than the initial estimate), a recent poll by Japanese news network NHK found that "81 percent of respondents say they disapprove of the plan to build the stadium without... View full entry
Two massive arches that form the backbone of the stadium's roof, a feature that critics blamed for raising construction costs, will remain part of the design. — usatoday.com
When confronted with Zaha Hadid's too-big and too-costly design for the 2020 Olympic National Stadium, Tokyo officials decided to go ahead with the designs anyway – or else, add "too late" to that list of descriptors. Any additional major changes to the design (Hadid already scaled back the... View full entry
Japan’s Sport Council on Thursday awarded a contract to design and construct a centerpiece, billion-dollar national stadium that forms a key part of Tokyo’s bid to host the 2020 Olympic Games to lauded U.K. firm Zaha Hadid Architects. — blogs.wsj.com
Previously: New National Stadium Japan Competition Unveils 11 Finalists View full entry
Eleven finalists have been announced today in the international design competition for the New National Stadium Japan, including design heavy hitters like Zaha Hadid Architects, SANAA, UNStudio, and Toyo Ito. The finalists, announced by the Japan Sport Council (JSC) and jury chair Tadao Ando, were selected from 46 entries to proceed to the second and final competition round. The final winner will be selected on November 7 and officially announced later that month. — bustler.net