From Permit (also bidding process happens here) -> Construction Sets
Typically, in Canada, we go for Permit around 75% finished set. Ensuring that all the code related stuff are met. Then while the city is reviewing the permit set, we finish off the rest of the drawing. And issue a tender set to the client, who will distribute to the GCs betting on the project.
Yeah you're making a lot of assumptions based on your own experience. I've done the process every which way and they're all valid depending on the circumstances.
Aug 1, 22 5:55 pm ·
·
Block this user
Are you sure you want to block this user and hide all related comments throughout the site?
Archinect
This is your first comment on Archinect. Your comment will be visible once approved.
How come tender period is different in the US compared to Canada?
In Canada, most firms I worked at
We go from Permit -> Tender -> Construction sets.
In US, most firms go
From Permit (also bidding process happens here) -> Construction Sets
Typically, in Canada, we go for Permit around 75% finished set. Ensuring that all the code related stuff are met. Then while the city is reviewing the permit set, we finish off the rest of the drawing. And issue a tender set to the client, who will distribute to the GCs betting on the project.
It depends and there is no standard. I have both types of projects on my plate ATM.
Yeah you're making a lot of assumptions based on your own experience. I've done the process every which way and they're all valid depending on the circumstances.