The Bronx County Hall of Justice is an 11-story, 775,000 square foot complex located on a 2½ block site. It also contains an underground parking structure for 240 cars. Hill provided construction management, program change management, change order processing, and negotiation, construction inspection, schedule and delay analysis, claims analysis and support and project closeout. As Inspector, Mr. Gant coordinated the mechanical, electrical and plumbing elements of the project with contractors and the design engineer. He also monitored construction of the HVAC system, plumbing work and the fire protection system, and reviewed all work completed by MEP contractors for all applicable codes.
Status: Built
Location: Bronx, NY, US
My Role: PROJECT INSPECTOR - MECHANICAL