The U.S. Department of Housing and Urban Development embraced the trapezoid, dubbed Iberville-Treme, along with an exhaustive New Orleans plan that called for 2,314 apartments constructed within 54 months.
Yet after 48 months — four years — the work in New Orleans is far from done.
If construction continues at the same pace in coming years, the promised 2,314 apartments won’t be complete until 2026.
— nextcity.org