Apr '14 - Nov '14
After the concrete had set we began removing the boxing from the sides of the concrete slab in order to let it cure and so we could continue wetting the slab during this process. We also began raising the walls on the bathroom pod so that we could start cladding the exterior in preparation for the... View full entry
A question was asked about the pre cast concrete we have been working on as to what exactly was the pre cast concrete for.To clarify it is the floor of the bathroom and laundry.These are some drawings that illustrate the area that is the concrete slab we are pouring off site and how it will be... View full entry
The team continued work on the wall panels by fixing support bars for the windows in the openings as well as started to clad the external walls on the north and south façades.This cladding process involved painting the wall panels, laying and fixing the 'z' and head flashings we had made for the... View full entry
Over the last few days we have been working on the steel reinforcing in the pre cast concrete slab. This was a difficult process to get right and took some time to complete the many links and ties to construct the cages of steel.After we had completed this the engineer came to site to check that... View full entry
Before we could fix any RAB board to the wall frames we needed to check that the wall was square and had not grown due to creeping measurements as we constructed it. Once we had check these we were able to apply RAB board to the exterior face of the walls in place of standard building paper. All... View full entry
With only a few wall frames left to complete we are almost done with the first step of the prefabrication process. Next we will move onto fixing rab board to the frames which will replace building paper. This is to ensure each wall panel is braced while being transported to site and erected. We... View full entry
Today we started the first step in our construction phase of studio 19. We began the day with a tutorial by James from crate construction on how to frame a wall. He went through nailing and cutting techniques, as well as important things to think about while framing the wall. We then proceeded to... View full entry
The next step in our preparation for the build phase of the project was to familiarise ourselves with the tools we would be using. Dave shared his knowledge with us a showed us the correct was to use the tools as well as explaining the dangers of the tools we were using. Some of the students had... View full entry
Wednesday 4th June, 2014From Resource Consent to Building Consent, it's now down to the nitty gritty for our kaumatua house, the aim being to make it a buildable and plausible design. Our four teams continue to work on the four core areas, thus making our own groups: the floor team, the roof... View full entry
After taking a broad range of design alternatives and amalgamating them into one design we presented this scheme to the clients. With a positive response from the clients and discussions about materials we will continue working to the detailed design for our next presentation. View full entry
After receiving feed back from the Clients for each scheme and assessing each others work we have the difficult task of bring together four very good and quite different schemes into one design. View full entry
Team Wha: Aseel Al-azi, Craig Pauling, Georgia Hay and Rory Keegan. View full entry
Team Toru: Waseem Chiraagh, Hannah Stephenson, Ameline Liew and Angus Beaton. View full entry
Team Rua: Jack O'Neill, Hannah Smith, Samuel Lawson and Lisa Humphrey. View full entry
Team Tahi: Jonnel Mamauag, Matthew Beneka, Jessica Hulme and Ashleigh Smith View full entry
So after a few weeks of designing the four group had a presentation to the Clients at Ngāti Whātua O Ōrākei head quarters. These presentations went well with the clients showing enthusiasm in the work the students had done thus far. View full entry
The different teams working on their designs in studio at UNITEC. View full entry
After two days of intensive studio we had some conversations surround what the different groups had come up with. Some good work has come out of such a good time but also a lot of questions raised, more work to be done still. View full entry
Took a couple of hours out on the second day up at Mangawhai to look at some of the architecture in the area. Dave showed us around Mangawhai and some of the work SGA has done in the area. View full entry
Studio 19 is a collaboration between UNITEC and Strachan Group Architects (SGA). Third year architecture students are given the opportunity to work along side SGA to design, document and build a project. The Brief from Ngāti Whātua O Ōrākei was to design of a master plan of eight houses for elderly tribe members. One of these houses is to be documented and built by the students.