- Stage D+ > Post-Planning > Pre-Construction
- New External Cladding Enclosure design and co-ordination for Public Realm retail units and the New Entrance to the West Stand Hospitality Building Extension,
- Designing the External Wall System design for new West Stand Accommodation Building using a Modular system while incorporating the manufacturers details.
- New Ticket Office Building Design and co-ordination with remaining new external cladding for the Existing Stadium,
- Games Announcement Booth facing the Community Track Re-Planning and detail design development.
- Planning Submission for Stage D+ with new External Facade development and new Halo and Service Pods Option surrounding the Stadium Perimeter,
- Large Scale Elevations Development from the 4 sides of the Stadium, which utilised 3D Schematic Models in Microstation,
- Stage E development of the retractable Tier design, including SPS Detailing of the Seating Tiers and Wheelchair Platform Design development at the top of the tiers facing the pitch,
- New Stadium Roof Design Development following a value engineered solution to cut down Construction cost induced by geometric and constructional complexity,
- Photo Finish Booth design development including construction solution to incorporate the diamond profile Main Roof Structural Ge-ometry,
- Main Roof Polycarbonate Cladding development, including construction detail development for connection joints within the roof and to the main stadium compression truss.
- Liasing with Structural Engineers to assess the Main roof construction details and sequence of erection and assembly on site,
- Developing physical scale model for the Main roof details for client and consultant meetings,
- Developing the 3D model for co-ordination of the Roof Prototype prior to construction of Main Roof on Site,
- West Stand Hospitality building IFC Development to include interior fit-out packages along with external facade design from stage D+ to construction on site,
- 1.5 years spent on-site for development of the construction packages while liasing with the design team of 20 + External design consultant co-ordination,
- Liasing in the design team meetings to assess the program development and how the packages require to be delivered to prevent any delays in the construction program,
- Initiating Design Change Requests to allow optimised schemes to be executed during the construction works, which required complete co-ordination between the internal and external design teams while maintaining the delivery of all related construction packages on time according to the Construction Program,
- Construction Package development includes :
- Drylining: 4 levels of the stadium, including public realm to hospitality, which includes an entire new storey on level 4,
- External Facade: Glazing and Aluminium Louvre and Panels development for the Main entrance to the West Stand Hospitality Building, - Internal glazing: Developing Glazing scheme for the internal spaces to separate the hospitality Spaces from the circulation Spaces,
- Incorporating the new glazing onto the existing internal parapet, and further developing the parapet details to modernise the entire composition, hence enhancing the existing condition from the original stadium,
- External Soffit: Aluminium Soffit development outside the Podium Concourse level and at high level above the new Extension storey oin level 4. Co-ordination with lighting designers and M & E Engineers to incorporate the service elements to facilitate the Fire Protection Strategy,
- Internal Ceilings: Developing new internal Ceilings while removing many ceilings as a result of new layouts and associated construction elements including drylining and lighting designs,
- Room Data Sheets: Development for the entire stadium while maintaining the existing features to allow the finalised finished to be applied and verified on site prior to opening of the games,
- Finishes Schedule: Finished schedule development includes Floor, Walls, Ceilings, Sanitaryware, Special Fittings/Fixings.
- Record Set Documentations for Contract Closeout and final verification of design delivery,
Status: Built