Kaiser Permanente Moreno Valley Medical Center

FACTS:
PROJECT NAME Kaiser Permanente Moreno Valley Medical Center
SIZE 93,700 GSF GSF
COMPLETION DATE 2023
LOCATION Moreno Valley, CA
CLIENT Kaiser Permanente
SERVICES Master Planning, Land Entitlement, Programming, Medical Planning, Architecture Interior Design
SCOPE The Moreno Valley Medical Center project scope includes a 93,700-sf,
two-level diagnostic & treatment (D&T) building addition and
22,700-sf replacement central plant to the campus’ existing 104-bed
hospital. Master planning and land entitlement were undertaken that
includes the D&T expansion, central utility plant replacement, and
future additions of a new bed tower and medical office building. The
D&T addition includes a 6-OR and 2 IR interventional suite, an
all-new imaging, clinical lab, central sterile and 6-bed NICU
departments. The new central plant resides in a new building adjacent to
the hospital.

Professional Role

As part of the Construction Administration Team I have responded to contractor RFI's and Submittals. I have coordinated ACD's, AMC's, and NMA's with the contractor and consultants for submission to HCAI offices or Field Staff. I created and maintained the NMA log as required by HCAI CAN 1-7-153, which was implemented while the project was well under construction. I have participated in weekly Owner-Architect-Contractor meetings. I have coordinated items with the owner and contractor which were added to the scope to ensure the client's happiness and successful utilization by the end users.



Construction Videos:
https://gilmanconstructionmedi...

Architects Website:
https://coarchitects.com/proje...

 
Read more

Status: Under Construction
Location: Moreno Valley, CA, US
My Role: Designer / Coordinator
Additional Credits: CO Architects, Inc.
Whiting-Turner Contracting Co.

 
Steel Frame Completion and Prep for Steel Deck Concrete Pours. Photo Credit: Crystal Lomeli
Steel Frame Completion and Prep for Steel Deck Concrete Pours.
Photo Credit: Crystal Lomeli
Interior Framing Progress. Photo Credit: Crystal Lomeli
Interior Framing Progress.
Photo Credit: Crystal Lomeli
D&T Addition Shown to Right of Existing Building. Render Credit: CO Architects, Inc.
D&T Addition Shown to Right of Existing Building.
Render Credit: CO Architects, Inc.
New Drop-Off to Serve New and Existing Program. Render Credit: CO Architects, Inc.
New Drop-Off to Serve New and Existing Program.
Render Credit: CO Architects, Inc.
New Entrance and Lobby. Render Credit: CO Architects, Inc.
New Entrance and Lobby.
Render Credit: CO Architects, Inc.
Lobby Entrance Canopy and Front Doors. Render Credit: CO Architects, Inc.
Lobby Entrance Canopy and Front Doors.
Render Credit: CO Architects, Inc.
Prefabricated Plumbing Panel Used to Save Time on Plumbing. Installation. Credit: Crystal Lomeli
Prefabricated Plumbing Panel Used to Save Time on Plumbing. Installation.
Credit: Crystal Lomeli