Last Two year performance

2015   Performance

                                                                                                                 Sebastian Zysman

 

1-2-2015 Webster D.

Scope of Work :DOB onto completion

Schematic design review (code and guidelines)

HPD submission, DOB Submission, HPD Comments review and answers, DOB comments review and answers, Fire protection & ZD1 plans.

Construction documents, MEP and Structural Coordination.

3-5-2015 CROTONA B.

Scope of Work :DOB onto completion

Schematic design from scratch (code and guidelines)

HPD submission, DOB Submission, HPD Comments review and answers, DOB comments review and answers, Fire protection & ZD1 plans.

Construction documents, MEP and Structural Coordination.

3-18-2015   STRIVERS.

Scope of Work :DOB onto completion

Schematic design review (code and guidelines)

1st floor and cellar review coordinating supermarket interior design

DOB Submission, comments review and answers, Fire protection & ZD1 plan.

Construction documents, MEP and Structural Coordination (pour concrete)

5-22-15  411-421 35W St.

 Scope of Work: drafting services

Develop of wall section and construction details structural coordination   W/Doris

 

 

6-22-15 Rodney

Scope of work DOB Submission

Mark ups provided by Ed and Adrian, 1/8” Scale, 1/4” Scale   details wall section and schedules reviewed

6-22-15  150 Union St

Scope of work Mark ups &  DOB Submission

Mark ups provided by  Tom and Uzzi DOB objection answers, 1/8” Scale, 1/4” Scale   details wall section and schedules reviewed

7-06-15 Fulton

Scope of work HPD ,DOB Submission, IFC

Schematic design Inclusionary, Efficiency, massing studies   (code and guidelines)

HPD submission and answer objections DOB Submission on hold

7-06-15 Johnson  Ave

Scope of work Schematic design

7-06-15 100 Union St

Scope of work Schematic design

7-06-15  4th Avenue

Scope of work Mark ups &  DOB  Re Submission

Mark ups provided by Tom and Ed   1/8” Scale, 1/4” Scale   details wall section and schedules reviewed

9-03-15  W 28  st

Scope of work Mark ups  & Layouts review

Mark ups provided by Steve 1/8” Scale, 1/4” Scale   details wall section and schedules reviewed

9-07-15  W 28 st

Scope of work Mark ups, stair & layout reviews

 

9-07-15  810 Fulton St

Scope of work drafting services 

Wall sections exterior details window details ramp and detention tank.

2016   Performance

2-8-2016    304 w 150th St.

DOB onto completion (Retaining + DOB completion)

4 -25-16 Schematic design review (apartments didn’t meet HPD guideline)

5 -2-16 Schematic design & DOB review (encroachments)

9-10-16 Mark ups, new drawings and details requested by Quality  department   after DOB submitting for IFC set 80% addressed. No consultant coordination done

2-8-2016    321 e 60th St.

Scope of   Work: Developing wall section and details as per Doris and Ed request

2-25-16   King square. A

Scope of   Work: DOB onto completion

3-3-16 Schematic design & DOB review Parking in the building no cellar

5-23-16 Schematic design & DOB review, apartments at 1st floor (not allowed by MX-1 City of Vermont guideline)

5-27-16 Schematic design & DOB review Cellar back no mechanical Rooms at 1st floor

9-10-16 Issue to DOB 90%

5-16-16   King Plaza  B

Scope of work Schematic design

 5-23-16 Schematic design review, apartments at 1st floor (not allowed by MX-1 City of Vermont guideline)

6-20-16 Schematic design review, drastically reduced cellar size (Rock on site catch) no room for bulk storage requested by HCR

7-29-16 Schematic design submitted

 

5-26-2016  207/9w 140th St.

Scope of Work: DOB onto completion 

4-7-16 Schematic design review (no CMU structure)

9-5-16 Schematic design review (encroachments)

6-30-2016 Miscellaneous

Scope of work:   Crotona A&B condo plans, Webster “D” revised elevation as per owner request

8-12-20 Rodney

Scope of work 95% completion

As per owner request Cellar elevation reviewed floor plans details and stairs Sections and elevation dwg’s reviewed, followin gDesign department comments.

9-28-2016 Rodney 

Scope of work  Drawing services IFC

Addressing Design  department comments and develop of new details requested by Quality Department , in the proses we catch more miss coordination  typos and mistakes and we were working on them

 
Read more

Status: Under Construction
Location: New York city and New york State
My Role: Manager

 
Crotona B
Crotona B
Webster D
Webster D
304 150 West Street