Masfout Hospital

30 Bed General Hospital Prototype, Masfout, Ajman

Masfout hospital is first 30 bed general hospital prototype built in the Emirates of Ajman for the Ministry of Public Works. Preliminary discussions were held between the ministry of public works and UPA in the year 2007 to develop the design along with the medical equipment. The project comprises of ground floor for all functions of the hospital, and the first floor for inpatient wards only, but the services are located in mezzanine floor to serve both up to first floor and down to the main ground floor. This service area is connected by service bridge to the service block which is located at the side but away from the main hospital. The design and the selection of the material is developed to harmonize the surrounding  area which is of mountain nature. The Originally design allow the future expansion up to 60 beds. The design developed as joint venture between General Planning & Urbanism Planning Architecture. Project MCK did consultancy services for medical planning and equipment. UPA continued  the project up to site supervision and final delivery to client.

Client: Ministry of Public Works (MOPW), Dubai

Design Company in Charge: Urbanism Planning Architecture

Design: Urbanism Planning Architecture and General Planning

Architect:  Arch. Paolo Lettieri, Arch. Dagmar Sestak

Project Team: Paolo Lettieri, Dagmar Sestak, Aswan Zubaidi,  Andrea Bambini, Giuseppe Monti, Haider Ismail, Antonina Gucciardi, Francesco Prennushi, Marta Candiani, Roberto Delponte, Pietro Gottardi, Alessio Eberlin, Pierolivo Lunardelli, Simona Panfili, Irene Tchimorin, Giorgio Tommaselli, Maria Marta Zandonà.

Healthcare Design and Medical Equipment: Progetto MCK

Site Supervision: Urbanism Planning Architecture

Site Supervision Team: Aswan Zubaidi, Sahar Yousif, Tawfik Chams, Rawad Alia, Omar Akeedy, Dong Gun Lee, Mohamed Mokhtar Eid,  Haider Ismail, Kassim Kassim, Younis Karim Al Jewari, Mohd Hadithi, Ahmed Hammadi, Mohd. Hafiz,  Iyad Kassab,  Ayman Hussein Khalil, Paolo Lettieri, Ali Majeed, Hany Nawar , Firas Jhonny Raheel, Firas Salman, Nasser Al Talib.

Client: Ministry of Public Works - UAE

End User: Ministry of Health - UAE

Contractor: John Sisk & Son Construction

Size: 6.920 sqm built up area, 42.000 sqm plot area

Cost of the project: 22.000.000 €

Project duration: Design 18 months / construction 24 month

Photo Credits: Arch. Paolo Lettieri

 
Read more

Status: Built
Location: Fujayrah, AE