Clinton Public School District / Clinton High School Athletic Complex

The Work included a new combination Football/Soccer Field *(Phase 1), home & visitor stadiums, visitor locker rooms, concessions building, entry structures, regulation high school running track, synthetic turf, track and football storage facility, and at the opposite side Campus was the Tennis / Softball Facilities that included tennis courts, regulation softball field,and  toilet facilities (Phase 2). Approximate construction cost of both Phase 1 & 2: $6,600,000.00. This Project was designed by nine separate Contracts saving the district approximately $400,000.00.

 
Read more

Status: Built
Location: Clinton, MS, US
My Role: Architect
Additional Credits: Mike Godfrey Structural Engineering, Jon Rice Electrical Engineering, Atherton Mechanical Engineering, GeoScience Soil Geotechnical Services.