Archinect
Q Nicole

Q Nicole

Tulsa, OK, US

anchor
PFT-School-
1 more images  ↓

Patrick F. Taylor Science Technology and Academy

Job Captain for the Patrick F. Taylor Science and Technology Academy [$34M budget]
Base bid square – 84,620 SF; two classroom pods, cafeteria, and conference center, administration office, library with common area, and green roof; Alternate 1=19,830 SF; classroom pod; Alternate 2=15,208 SF; gymnasium/auditorium…Total SF – 119,658.Developed first- and second-level floor plan, reflected ceiling plan, finish floor plan, wall finish plan, and interior/exterior elevations. Conducted product representative meetings. Conducted material research, all exterior elevations, window and interior elevations for base bid, and alternates 1 and 2.

Project Manager for the Alternate 2 gymnasium from design development to construction documents; coordinated with engineering consultants and Verges Rome, the joint venture partner.

 
 Read more

Status: Under Construction
Location: Avondale, LA, US

 
PFT-Gym

Back to Top  ↑Back to Project List...

Please wait... loading